Mont-Louis Wind Power Project The plan of wind force Mount-Louis count 67 aeolian GE 1,5s producing 100,5 MW. It is nowadays to eat the medium stage of development. In reply to the approval of the proposal of Northland Power outside the
invitation to tender of 2004, Hydro-Quebec establishes an understanding of 20
years for the purchase of electricity produced by this plan.
Jobs will start towards the end of the summer, 2009 with the building of roads. The engineer and businessman for the rest of the power station, Genivar-Blattner, will carry out main jobs – foundations, erection of the aeolian and electrical facilities – in 2010. The beginning of commercial working is envisaged for December, 2010. Environmental impact evaluations have not started yet. The control of
means is under way, with the addition of three meteorological towers more the
end far from most and the beginning of the autumn, 2005, en more possible
possible is already sur the site. |